Grace Driveway Work. Postponed till 21st.

Driveway Project Update: June 12th

  • The Weather: Our paver is keeping a close eye on the rainy weekend forecast and has recommended pushing the work back one week.

  • Sunday Access: Because of the delay, the driveway is expected to be fully open and operating as normal this Sunday.

  • We will keep everyone updated as plans lock in!


On Friday, May 29th, work officially began on our driveway at Grace. The crew cut out the old, damaged sections and filled the holes with fresh asphalt.

Upcoming Driveway Closure: Sunday, June 14th

The next step is sealing and restriping, which will take place starting Friday evening, June 12th, and run through the weekend. This means we will not have access to the driveway on Sunday, June 14th.

For that Sunday, we will park in the grass near our sign on Cashmere Blvd. The back door to the fellowship hall will be open for entry.

When scheduling this project, we had to choose between blocking access during the week or over the weekend. Closing the driveway during the week would have disrupted the Alzheimer’s daycare. Because it is difficult for many of those patients to walk long distances, we decided it was best to have the work affect the church over the weekend instead.